N-9 Parking Structure Dismantle – NSA

 

Access Contracting Group was awarded the opportunity to dismantle a Parking structure for the National Security Agency through the General Contractor Chugach Government Solutions.  This project was completed in 30 days instead of the 60 days given to us. Thank you, Chugach, for allowing us to complete this project  and we look forward to working with you in the future.

Demolition:

  • Mobilize manpower & equipment
  • Install temporary chain link site fence on perimeter of work area 
  • Remove & dispose of all signage/supports
  • Remove & recycle chain link fencing
  •  Remove all electrical equipment, wiring & conduit
  • Remove all trench drains, plumbing, downspouts, & standpipes
  • Disassemble & remove all stairs & railings
  • Saw cut seam of concrete decks to release fasteners
  • Rig & pick concrete panels using 100 Ton crane truck
  • Place deck sections on flatbed semi trailer to hauled off site immediately
  • Unbolt & remove structural steel framing
  • Column base anchors shall be cut flush & driven below existing asphalt to eliminate trip hazard
  • Remove & dispose of perimeter bollards as indicated on drawings
  • Remove & dispose of concrete ramp structure & associated footing
  • Back fill & compact depressions left from structure removal with RC-6 material
  • Project dust control measures for demolition work
  • All workers U.S. Citizens